Measure E Construction Updates

  • Backhoe and construction workers digging trench

    MVLA is proud to offer innovative, award-winning academic programs that prepare our students for college and jobs of the future. Our high schools rank amongst the best in the state and the nation, yet years of sustained enrollment growth mean we face significant overcrowding. Additionally, aging classrooms, labs and student support facilities at each of our campuses are in need of repair and modernization to meet 21st-century educational standards.

    Mountain View Los Altos High School District (MVLA) has worked closely with our community to complete a comprehensive Facilities Master Plan to address facilities’ needs and sustained enrollment growth in our schools. Through regular public board meetings, site meetings and a district-wide survey, we worked with our community to develop a long-term solution for current and future students.

    In February, the MVLA Board of Trustees unanimously voted to place a $295-million bond measure on the June 5, 2018 ballot. Measure E passed with 66% of the vote. This local source of funding will help combat growing enrollment in our district and upgrade aging classrooms, labs and school facilities.

    Based on what we have heard from our students, parents, teachers and community, priority projects funded by this bond measure will include:

    • Adding classrooms to accommodate growing student enrollment and prevent overcrowding
    • Providing facilities to expand programs in science, technology, engineering, arts and math
    • Updating aging classrooms and replacing old roofs, outdated plumbing and inefficient wiring and electrical systems to meet modern safety standards
    • Expanding libraries, cafeterias and other student support facilities to accommodate growing student enrollment
    • Equipping classrooms and labs with 21st-century learning technology

     

    Measure E Construction Disturbance Coordinators

    Construction of new school facilities are underway and will continue for several years at both Los Altos and Mountain View high schools.  Permitted working hours are:

    LAHS

    Weekdays: 7 a.m. – 7 p.m.

    Weekends: Saturday, 9 a.m. -6 p.m.; Sunday, none

     

    MVHS

    Weekdays: 7 a.m. – 6 p.m.

    Weekends: Saturday and Sunday, 9 a.m -5 p.m. with approval from the City of Mountain View.

     

    If you have a concern about construction activities on one of the MVLA campuses, our construction contractor has two dedicated Disturbance Coordinators:

    • Los Altos High School: Roy Atkins 408-828-2909
    • Mountain View High School: Ken Judd 925-628-0186

    If you have a question for the MVLA High School District about construction plans and activities, email: community@mvla.net.

    You can read quarterly Measure E construction updates below.

  • January - March 2019

     Construction workers at hole in sidewalk with backhoe

    February 2019: MVLA is holding Interim Housing pre-construction meetings with the Kramer team. These meetings get all the contractors, project architect, inspector, and construction managers in the same room to review project expectations and timelines. Temporary construction fencing is scheduled to go up this month, with underground trenching and fire hydrant connections taking place during the February break.

    March 2019: Heavy earth-moving equipment can be seen on the Los Altos and Mountain View high school campuses as crews trench, scrape, and level soil to get the underground utilities ready for the portable classrooms to be used to house learning while the new classroom buildings are constructed. The rains delayed things for a few days, but we continue to make appropriate progress!

  • April - June 2019

    April 2019: While bringing the end of drought to our state, the spring rains have caused some delays in the installation of the temporary classrooms, but progress is being made, albeit muddy progress. The following projected dates are tentative because more rain is forecast for the coming weeks.

    At Los Altos High School, building pads are nearly fully prepared for the portable buildings and we expect the portable buildings to be delivered and installed starting during spring break - week of April 15. We anticipate the portable classrooms will be fully installed about May 20, and that teachers will move into this interim housing week of June 10.

    At Mountain View High, the ground is extremely saturated and has made compaction efforts ineffective, delaying the schedule. Weather permitting, the building pads could go in during the week of April 29. Once the building pads are complete, portable buildings will be installed, projected for the week of May 6, then teachers could move into their temporary classrooms during the week of June 10.

    May 2019: 

    At Los Altos High School, building pads were completed and the portable buildings installations were done over spring break. Now electrical connections, fire alarms and asphalt paving are in progress.

    At Mountain View High School, the ground has been extremely saturated by rain so the portable building installation was delayed until this month. After soil treatment to harden the ground, building pads were completed and the portable buildings were delivered and installed mid-May.  Electrical and paving work will soon follow.

    At both schools these portable classrooms will remain in place until construction of the new classroom buildings is complete. Teachers should move into their temporary classrooms in mid-June, after summer break begins.

    The MVLA District is still waiting for California Division of the State Architect review and approval of our new classroom projects.  No new construction can begin until the project gets that approval.

    This month, the seven-member Measure E Citizens Oversight Committee (COC) had their first meeting.  Associate Superintendent for Business Services Mike Mathiesen and Rick Kramer of Kramer Project Development Company facilitated the meeting, including an overview of COC role and responsibilities, bond project list, and bond expenditures to date. This committee will meet the statutory requirement of the COC annually reporting to the board by presenting a one-page report at an upcoming MVLA board meeting. Future annual reports will be more robust as there will be much more to report. The COC plans to meet at least twice a year - once in February/March to review the performance audits prepared by the district’s auditor and a second time in the summer/early fall that includes a site visit of project.

    June 2019: 

    Installation of the temporary classrooms (interim housing) is coming to a close, as is the school year. The asphalt work is complete, and most of the electrical is done as well. Classroom technology like projectors and speakers will be installed later this month. 

    At both sites, we are setting up temporary fencing, power, and water to prepare for the official start of building construction, pending DSA approval. We have also started some small demolition to prepare for moving portable, temporary buildings.

    Sound barrier walls are going up at both schools to reduce some of the noise impact on neighbors’ homes that are adjacent to our shared fences.



  • July - September 2019

  • October - December 2019

architectural rendering of new engineering classroom building